IMPORTANT NOTICE FROM THE PARISH COUNCIL
IMPORTANT NOTICE FROM THE PARISH COUNCIL
IMPORTANT NOTICE OF WATER MAINS RENEWAL AT HILL FARM ROAD
START DATE : 7th FEBRUARY 2022 – END DATE: 17th APRIL 2022
Approx. 1km of water main replacement along Hill Farm Road.
From the junction of West End / Hill Farm Road to the junction of the A505.
Work will be starting on Monday 7th February at the A505 junction progressing North for a period of approx… 8 weeks.
In order to complete the works safely there is a need to enforce some temporary road closures.
Initial 400m section to be renewed under one-way system allowing traffic to exit onto the A505.
Duration approx.. 3 weeks.
Road closure to then come into force from 28th February 2022.
Trial holes to be done in week 1 to determine whether this needs to remain closed or can be reverted back to one way.
Best case: Road closure for 1 week
Worst Case: 3 week closure with road closed from 28th February – 20th March.
Finish with 3 way traffic lights at the junction of Hill Farm Road and West End.
Pedestrian / Cyclist and Access to properties and businesses will be allowed at all times, unless otherwise agreed.
It is hoped that disruption will be kept to the necessary minimum.